The Economic Development Committee of Evanston met on Wednesday to confront a looming deadline imposed by the American Rescue Plan Act (ARPA). The city received roughly $43 million in ARPA aid beginning in 2021, of which $3 million was earmarked for the Evanston Thrives action plan. Less than $1 million of that allocation remains unspent, and officials must expend the balance by the end of the year or return it to the federal government.
Committee members, led by Councilmember Clare Kelly of the 1st Ward, were asked to recommend how to allocate the exact figure of $934,579.34. Kelly voiced the pressure of the ticking clock, saying, “I’m just concerned that we’re under the gun so we’re going to spend a million dollars. But I guess we don’t have a choice because we’re under the gun, so I guess that’s my point of frustration.” The sense of urgency was shared by staff, who earlier had imagined lighting nine Metra viaducts but now must narrow the scope to two.
Funding options on the table
Economic development director Paul Zalmezak explained that two bridges—Church Street and Davis Street—have been identified as viable candidates for the remaining ARPA dollars. The original plan called for artistic illumination of both structures, with costs estimated at $491,678.50 for the Davis Street bridge and $446,975 for the Church Street bridge. A third, minimal amount of $4,074.16 would be needed to cover leftover expenses, leaving no money for additional placemaking projects.
Three distinct proposals were laid out for council consideration:
- Option A would fund both bridge lighting projects in full, consuming the entire $934,579.34 and requiring a negligible supplemental amount.
- Option B would drop the Davis Street bridge, directing funds toward Church Street lighting ($447,000), a $245,000 placemaking package for Callan Plaza at Howard Street and Callan Avenue, a $45,000 upgrade for City Center Plaza near City Hall, and an additional $254,750 for a suite of “design packages” that would prepare future projects. This scenario would still need $57,145.66 from other sources.
- Option C, amended by Councilmember Matt Rodgers of the 8th Ward, mirrors Option B but eliminates the design-package allocation, leaving $197,604.34 available for other uses.
Rodgers highlighted that Callan Plaza already benefited from $225,000 of Howard and Ridge TIF (tax increment financing) funding, suggesting that ARPA cash could complement, rather than replace, existing investments.
Debate, amendments, and the path forward
During the discussion, several voices underscored the visual and economic impact of the bridges. Acting Mayor Jonathan Nieuwsma emphasized the importance of the Church Street bridge for downtown businesses, noting the proximity of the Northlight Theatre and its role as an economic driver. Downtown Evanston executive Andy Vick added, “Creating a showpiece bridge at a key gateway is a good thing for this entire community; people will talk about it, they’ll want to see it, and it could set a standard for future projects.”
Opposition came from local business owner Cheryl Judice, who warned that the current state of the Church Street bridge area detracts from Evanston’s image to visitors. Meanwhile, Katie Boden, the city’s economic development coordinator, described the lengthy negotiation process with Union Pacific, which owned the rail right-of-way, as “very extensive” and a major source of delay.
The committee ultimately leaned toward Options B or C, with a particular focus on improving the Church Street bridge while also investing in Callan Plaza and City Center Plaza. The final recommendation will be formalized in a written report and presented to the full City Council at its meeting on Nov. 9, where councilors will vote on how to allocate the remaining ARPA resources.